We’re investing nearly $30 million in road improvements in Campbell Heights to better serve the growing needs of businesses, industries and the city.

Campbell Heights plays a crucial role in Surrey’s economic development by fostering businesses and industries. The Campbell Heights Business Park is one of Surrey's largest industrial and commercial hubs creating over 7000 jobs for the region.

Road improvements are needed to service the continued growth in Campbell Heights as it attracts new businesses and creates more jobs. Road improvements will reduce traffic congestion in the area, improve access to businesses, support growth and increase road safety for pedestrians and cyclists.

Project locations

  • 16 Avenue: 19000 block to 192 Street
  • 192 Street: 16 Avenue to 28 Avenue
  • 24 Avenue: 188 Street to 194A Street
  • 28 Avenue: 192 Street to 194 Street
  • 32 Avenue: 192 Street to 196 Street

    Map of locations:
Map highlights roads that will be improved.

 

Project design

Improvements include

  • additional travel lanes
  • new signalized intersections and improved traffic movements at intersections
  • integrated cycling-walking facilities


Below are artistic renderings of roads improvements. Actual roads may look different. 

192 Street (16 Avenue to 20 Avenue) 

Road with 4 lanes and multi-use path on one side.

 

192 Street (22 Avenue to 24 Avenue) 

Road shows 4 lanes with reduced median and multi-use path on one side and sidewalk, boulevard and bike lane on the other.

 

View Open House Presentation Boards for detailed road designs and cross-sections of all project locations.
 

Project timeline

Phase 1: 192 Street (16 Avenue to 28 Avenue) 

Construction is anticipated to begin summer 2025, with advanced tree clearing taking place along 192 Street between 16 Avenue and 20 Avenue in February.  

Future phases: 32 Avenue, 28 Avenue, 24 Avenue, and 16 Avenue

Construction will be done in future phases from 2026-2027.

Project impacts

To reduce traffic disruptions, road construction will be carried out in phases rather than all at once.

The widening of 192 Street between 16 Avenue and 20 Avenue will require removal of some trees within the existing road corridor. To minimize the tree impacts, have created a custom road design that keeps the road corridor as narrow as possible. Vehicle travel lanes will remain the same width as the standard for a City of Surrey arterial road.

Feedback

You can share your feedback in-person at the open house on February 6, 5-7:30 pm at Grandview Heights Aquatic Centre, or email engwebmail@surrey.ca