132 Street Improvements
The City plans to make improvements to 132 Street from 72 Avenue to 84 Avenue.
Project description
132 Street is an important north-south route linking the communities of Newton and North Surrey.
132 Street from 72 Avenue to 84 Avenue is an extremely busy corridor serving Newton businesses, industry and local residents. The City plans to make improvements along this section to reduce traffic delays, and improve traffic flow and road safety.
Project timeline
Improvements will be made in phases:
Phase 1: 72 Avenue to 76 Avenue
Construction will begin early 2025 and anticipated to be complete end of 2025.
Phase 2: 76 Avenue to 80 Avenue
Construction anticipated to start fall 2025 and to be complete 2026.
Phase 3: 80 Avenue to 84 Avenue
Construction anticipated to start in 2026.
Phase 1 Key Improvements
- road widening from two to four travel lanes to improve traffic movement
- adding multi-use paths on east side of the road to make it safer to cycle and walk
- installing a pedestrian crossing at Comber Way to make it safer to cross the street
- adding new left turn lanes to improve traffic flow
- upgrading bus stops to improve access to transit
The project will also involve replacing aging sanitary sewers and watermains along 132 Street.
Contact
If you have questions or comments, please contact the Project Delivery Division at 604-591-4253 or engineering@surrey.ca.