The latest data collected shows significant process on the City of Surrey’s Guaranteed Permitting Timelines.

April 26, 2022
Media Release

Surrey, BC – The latest data collected shows significant progress on the City of Surrey’s Guaranteed Permitting Timelines. To minimize the wait time between applying and receiving a building or rezoning permit, Surrey City Council approved Guaranteed Permitting Timelines in October of 2021.

“The goal of this program is to ensure building permits are expedited in a timely manner,” said Mayor Doug McCallum. “Not knowing when a building permit will be issued has long been a point of frustration for builders. Council’s implementation of a guaranteed timeline will result in less idle time for builders and more accurate completion dates for people looking to move into their new home or business space. The latest data shows that we are not only meeting our goals, but we are exceeding our targets in several areas. I would like thank staff for their quick work on this important initiative.”

The latest data shows in four of five categories processing times have met or exceeded targeted timelines:

   

Current
Processing Time

Average Processing Time

Average Processing Time

Permit Type Established
Guarantee
Targets
April 2022 Q1 2022 Q4 2021
Single Family 10 weeks 8.4 weeks
Below Target
9.4 weeks
Below Target
14.6 weeks
Above Target
Tennant Improvements 10 weeks 10.1 weeks
Above Target
8.0 weeks
Below Target
7.0 weeks
Below Target
Rezoning, Single Family 12 weeks 11.4 weeks
Below Target
8.6 weeks
Below Target
Not enough
data
Rezoning, Multi-Family,
Commercial, Industrial
16 weeks* Not enough data Not enough
data
Not enough
data
Site Servicing Reviews
(Servicing Agreements)
2.5 weeks 2.4 weeks
Below Target
2.4 weeks
Below Target
2.9 weeks
Above Target

*Add 4 weeks for project requiring ADP review

A number of initiatives have been implemented to accelerate Guaranteed Permitting Timelines, which include increasing staffing resources, expanding the online digital permitting portal, and the introduction of an expanded hours pilot program that extends the opening hours of City Hall to 8pm one day per week.

The full Corporate Report can be viewed here.