INTRODUCTION

The City of Surrey (the “City”) invites contractors to provide a quotation on the form attached as Schedule C (the “Quotation”) for the supply of the goods (if any) and services described in Schedule A (the “Work”).  The description of the Work sets out the minimum requirements of the City.  A person that submits a Quotation (the “Contractor”) should prepare a Quotation that meets the minimum requirements, and may as it may choose, in addition, also include goods, services or terms that exceed the minimum requirements.

SCOPE OF WORK

The Work covered under this project consists of the furnishing of all superintendence, overhead, labour, materials, tools, equipment, insurance, fuel, transportation and all things necessary for and incidental to the satisfactory performance and completion of  construction and renovation of South Surrey Indigenous Carving Centre, located at 13723 Crescent Road, Surrey, British Columbia in strict accordance with the Specifications and accompanying Contract Drawings and subject to all terms and conditions of the Contract Documents.

Furnish certificates confirming work conforms to requirements of authorities having jurisdiction.

INFORMATION MEETING

An information meeting will be hosted by the City Representative to discuss the City’s requirements under this RFQ (the “Information Meeting”).  While attendance is at the discretion of Contractors, Contractors who do not attend will be deemed to have attended the Information Meeting and to have received all of the information given at the Information Meeting.

At the time of issuance of this RFQ a meeting has been scheduled as follows:

Date:               Wednesday, November 10, 2021

Time:               1:30 p.m. (Local Time)

Location:         13723 Crescent Road, Surrey, British Columbia, V4P 1J4.

It is possible that some questions raised, and information provided during the Information Meeting may be the only source of critical information essential to prepare and submit a successful Quotation.  Contractors are responsible to ensure they are fully informed and have a clear understanding of the requirements.

ADDENDA

If the City determines that an amendment is required to this RFQ, the City Representative will issue a written addendum by posting it on the BC Bid website at www.bcbid.gov.bc.ca and the City website at www.surrey.ca (collectively, the “Websites”), and upon posting, any addenda will form a part of this RFQ. It is the responsibility of Contractors to check the Websites for addenda. The only way this RFQ may be added to, or amended in any way, is by a formal written addendum. No other communication, whether written or oral, from any person will affect or modify the terms of this RFQ or may be relied upon by any Contractor. By delivery of a Quotation the Contractor is deemed to have received, accepted and understood the entire RFQ, including any and all addenda.

All inquiries related to this RFQ should be directed in writing to the contact person named above.