Google Translate
Translation – Explanation and Caution

The electronic translation service on the City of Surrey’s web site is hosted by Google Translate. The quality of the translation may vary in some of the languages offered by Google. The goal of the basic translation is to capture the general intention of the original English material.

Google Translate is a free service and currently offers translation in over 50 languages. Unfortunately, not all the languages spoken in the City of Surrey are translated. Punjabi is one of the languages not currently offered, and to remedy the situation, the City has been in contact with Google and they have committed to making Punjabi available in the future.

The City of Surrey cannot guarantee the quality, accuracy, or completeness of any translated information. Before you act on translated information, the City encourages you to confirm any facts that are important to you and the decisions you make.

The City of Surrey offers interpretation services at all its facilities. If you have a question about the material you read on our web site, we encourage you to stop by a City facilities to discuss it. You can also contact the City at (604) 591-4011 to receive interpretation support.

The City is committed to enhancing the accessibility of its web site to all its citizens, and appreciates any feedback that it receives.

Chinese, Korean, Punjabi, Tagalog, Hindi

Local Area Service (LAS) Program

Local Area Service program is a neighbourhood improvement paid for by the owners of the benefiting properties. Some services may qualify for assistance from the City.

Typical services accommodated under the program are:

  • Pavement widening with concrete curb and gutters (including sidewalks and trees, as required);
  • Installation of street lighting;
  • Lane paving;
  • Water main extension;
  • Sanitary Sewer main extension;
  • Storm Sewer extension.

A LAS project can be initiated either by "Petition" or by "Council Initiative".

By Petition: Property owners may petition (through Preliminary Petition Form) the Council for a LAS defining the benefiting boundaries. To get approved by Council, the formal petition should be signed in favour by at least half (1/2) of the property owners representing at least half (1/2) of the assessed value of the properties benefiting.

By Council Initiative: Council initiated LAS programs will be published in the local newspaper and notification is also mailed to each benefiting property owner. Unless requested otherwise, the program will proceed.

The LAS projects are carried out on actual cost basis, which will be determined at the completion of the project. However, the following table provides approximate cost ranges to illustrate the order and magnitude of the costs.

Type of Work

Approximate Total Cost2 per Metre of Frontage

($/m)

Typical Owner's share of the Total Cost

Street widening (One side)1

600 - 800

50%

Street Paving (Overlay)

90 - 150

50%

Lane Paving

400 - 600

50%

Street Lights

250 - 350

100%

Sidewalk – Abutting1

200 - 300

40%

Sidewalk – Opposite1

200 - 300

20%

Sanitary sewer extension

800 - 1200

100%

Water main extension

250 - 600

100%

Storm sewer extension

800 - 1200

100%

Notes:

1 Sidewalk installation or street widening may require storm sewer works

2 Costs above are based on 2006 prices


For additional questions or to discuss initiating a LAS project with Engineering staff, contact the City Hall (at 604-591-4146).

Frequently Asked Questions on Local Area Service

Q1. How do I start the LAS project?

Discuss among the neighbourhood to determine the support for the project. Define the project boundary – from where to where the service is to be provided. Discuss with the City Engineering staff (contact 604-591-4146). If at least ½ of the property owners within the benefiting area are in support, collect a "Preliminary Petition Form" from the LAS Clerk at the City Tax Department (or download from the City web site), complete, and submit at the City Clerk's Office. A contact person (Leader) should be nominated by the owners and indicated in the Preliminary Petition Form.

Q2. Is signing the Preliminary Petition Form binding?

No, It is only an expression of interest. Your commitment will be expressed through "Formal Petition", which will be prepared and sent to you by the City on receipt of the Preliminary Petition.

Q3. Should I be an owner to sign the petitions? What if multiple owners exist? Are multiple owners getting more than one vote?

Only owners can sign. Each property has a single vote irrespective of the number of owners. In the case of multiple owners, the majority (more than 50%) of the owners must sign for a property to be considered in favour.

Q4. How do I know my cost?

Once the City receives the Preliminary Petition, a Formal Petition Form will be prepared with details such as properties benefiting, cost estimate attributed to each property, etc., and will be forwarded to each benefiting owner.

Q5. Is the cost given through the Formal Petition Form final?

No, it is only a cost estimate. Final costs will be assessed only after the completion of the project.

Q6. What are my choices? If I do not sign, should I pay?

If you favour the project, you will sign and return the Formal Petition Form – then you are committed to the project. If you choose not to favour the project, you can disregard the Formal Petition. However, if sufficient property owners sign the petition and project is approved by City Council, irrespective of signed or not, every property owner in the benefiting area will have to pay.

Q7. How is the total cost split between the properties?

The cost will be split proportionate to the frontage of each of the benefiting properties.

Q8. When should I pay, and should I pay at once?

At the end of the project, the actual cost attributed to each property will be determined and added to the tax roll. Owners can either pay in full at once or choose to pay over 15 years. The annual charges, in case of 15 years' payment, will include an interest component determined by the City at the time of approval of the project.

Q9. Is it a must that I connect to the utility service installed under LAS?

No, Owners can choose whether to connect to the City utility or not. No property will be connected to City network without an application from the property owner.

Q10. How do we get connected to the City main? Are there additional connection charges that apply?

As part of the LAS project, service connections are extended to the property line. Owners interested in connecting to City services should make an application at the City Hall (Engineering Front Counter). No connection charges shall apply.

However, the owners will have to install, at their cost, the necessary plumbing works within the property, for which a plumbing permit is required.

In the case of water service, as part of the plumbing works the owner will have to install a water meter chamber at the property line in accordance with the City Water Meter Standards and Specifications. Once the internal plumbing is approved, the City will install a meter. Contact the City Plumbing Section of the Building Division for permit charges including the cost of water meter: $150.00.

Q11. In the case of water service, on what basis would I pay for my water usage?

Per City By-law, all new water service connections must be metered. You would be charged on metered rate. Water Rate details are available in the City web site.

 

A PDF version of the Local Area Service Program Brochure can also be downloaded.