Inspection Procedures for Single Family Dwelling Permits

All Single Family Dwelling Building and Plumbing Permits for new construction are subject to the following inspection procedures:

To make a Frame Inspection request, you must first have the prior inspections:

  • Approval of Rough Plumbing Inspection(s)
  • Approval of Electrical Rough Wiring Inspection(s)

To make a Final Plumbing Inspection request, you must first have the prior inspections:

  • Approval of Building Insulation Inspection

To make a Final Building Inspection request, you must first have the prior inspections:

  • Approval of Final Plumbing Inspection(s)
  • Approval of Final Electrical Inspection(s)

Inspection requests not following these procedures for Single Family Dwellings cannot be scheduled.

Contact Building Inspections at 604-591-4231 for any questions or concerns relating to these procedures.